Project scheduling using dependency structure matrix JU Maheswari, K Varghese International Journal of Project Management 23 (3), 223-230, 2005 | 135 | 2005 |
Application of dependency structure matrix for activity sequencing in concurrent engineering projects J Uma Maheswari, K Varghese, T Sridharan Journal of construction engineering and management 132 (5), 482-490, 2006 | 84 | 2006 |
Design iteration in construction projects–Review and directions P Mujumdar, JU Maheswari Alexandria Engineering Journal 57 (1), 321-329, 2018 | 46 | 2018 |
Cloud computing to enhance collaboration, coordination and communication in the construction industry CB Amarnath, A Sawhney, JU Maheswari 2011 World Congress on Information and Communication Technologies, 1235-1240, 2011 | 45 | 2011 |
Identification and classification of change causes and effects in construction projects SPS Padala, JU Maheswari, H Hirani International journal of construction management 22 (14), 2788-2807, 2022 | 34 | 2022 |
Design coordination using cloud-based smart building element models A Sawhney, JU Maheswari International Journal of Computer Information Systems and Industrial …, 2013 | 33 | 2013 |
A structured approach to form dependency structure matrix for construction projects JU Maheswari, K Varghese Proceedings of the 22nd International Symposium on Automation and Robotics …, 2005 | 33 | 2005 |
Pharmacological studies of anti-diarrhoeal activity of Guettarda speciosa (L.) in experimental animals R Gandhimathi, AS Kumar, KKS Kumar, KP Kumar, JU Maheswari Journal of Pharmaceutical Sciences and Research 1 (2), 61, 2009 | 25 | 2009 |
A study on assessment of non-conformances using multiple domain matrix: A case study from metro projects JU Maheswari, VPC Charlesraj, GS Kumar, SPS Padala Procedia Engineering 145, 622-629, 2016 | 17 | 2016 |
Axiomatic design framework for changeability in design for construction projects SPS Padala, JU Maheswari Asian Journal of Civil Engineering 21 (2), 201-215, 2020 | 13 | 2020 |
Modeling design iteration using DSM and simulation JU Maheswari, K Varghese Proc., 24th Int. Symp. on Automation and Robotics in Construction, 2007 | 13 | 2007 |
Factors influencing design iteration with a focus on project duration KV Ummer N, J U MAHESWARI, V A Matsagar ASCE Journal of Management in Engineering 30 (1), 127-130, 2014 | 12* | 2014 |
Modeling a construction project in a matrix-based framework for managing requirement changes SPS Padala, JU Maheswari International Journal of Construction Management 23 (14), 2369-2390, 2023 | 11 | 2023 |
Application of Relationship Diagramming Method (RDM) for resource-constrained scheduling of linear construction projects JU Maheswari, VPC Charlesraj, A Goyal, P Mujumdar Procedia Engineering 123, 308-315, 2015 | 10 | 2015 |
Structured methodology for applying multiple domain matrices (MDM) to construction projects P Mujumdar, P Muraleedharan, JU Maheswari Proceedings of the 16th International DSM Conference, 299-308, 2014 | 10 | 2014 |
A study on ‘design thinking’for constructability SPS Padala, JU Maheswari Research into Design for Communities, Volume 1: Proceedings of ICoRD 2017 …, 2017 | 9 | 2017 |
A design iteration framework for construction projects P Mujumdar, JU Maheswari Proc. of the RICS Cobra, New Delhi, 2013 | 9 | 2013 |
Knowledge management for planning construction projects using dependency structure matrix VPC Charlesraj, JU Maheswari, KN Kalidindi, K Varghese 20th Annual ARCOM Conference 2, 831-8, 2004 | 7 | 2004 |
A study on DSM partitioning through case study approach P Mujumdar, S Bhattacharya, J Uma Maheswari ICoRD’15–Research into Design Across Boundaries Volume 2: Creativity …, 2015 | 5 | 2015 |
Modeling activity sequencing for construction projects using dependency structure matrix JU Maheswari PhD Thesis, Department of Civil Engineering, Indian Institute of Technology …, 2006 | 5 | 2006 |